Foundations and infill......8X57meters |
The foundations are already laid and the outline of the school
is already beginning to take shape....in my head anyway. It has been tough work
and all credit to Gordo and his team as they have worked around the clock (when
it isn’t raining). The entrance to the site is over some soft ground which has
increased the workload substantially. It means that all the sand has had to be
wheel barrowed closer to where the foundations are before the cement is mixed.
The bricks had to be left off 100m from where they are going to be used. It is
going to be a real lugging match; when it rains, the wheel barrow will be
useless and it will be six bricks at a time. I’ve been here before, it is a lot
of effort everyday and being on site everyday you can’t see the progress you’ve
made. God bless and keep them. We are at the height of the rainy season, the word on the street
is that it is going to be worse than 2009. The ‘road’ into the site is nearly impassable;
I’m getting passed on my motorbike with a few slips and slides with muddy boots
to show! The lorry is only making it in with 2m² of sand and has had to be
pulled out several times but we have found a back way into the site which could
be the solution.....there might be a question of trespassing....hmmm
![]() |